Vandana SharmaArchitectural Technician / BIM Technician
BC.27-29Bow Tie ConstructionResidential / Retrofit / BasementRIBA Stage 3-5

27 Buckland Crescent — Basement Retrofit and Extension

Renovation, energy retrofit, and extension of an existing family home at 27-29 Buckland Crescent, with a basement retrofit, rear extension, new green roof, and structural coordination with the engineer.

Location
Belsize Park, London
Scope
Basement and rear extension, flat 27/29 refurbishment
Structure
Underpinning, steel frame, geotechnical coordination
Stage
Technical design and construction

Project

Renovation, energy retrofit, and extension of an existing family home at 27-29 Buckland Crescent, Belsize Park, London NW3 5DJ. The scope covers a rear extension and full refurbishment of flat 27, a new green roof, and a balcony for the neighbour, along with renovation to flat 29.

Basement and structure

The basement works involve removal of the existing slab and excavation of soil, but not below foundation levels, followed by a new reinforced slab with high-performance thermal insulation and a waterproofing membrane. The back wall is underpinned over its entire length to connect with the new basement extension.

The lower basement FFL sits approximately 0.220 m below the current basement FFL and extends approximately 5.0 m into the garden. The rear basement wall is opened by 6.9 m and supported by a steel structure designed by the structural engineer. Geotechnical engineers designed the basement and underpinning to secure the four-storey building.

Role

Technical design and coordination with the structural engineer, including the basement and underpinning works, rear extension, and structural interfaces.

Details

SHEET 03Flat roof upstand detail
SHEET 04Flat roof rooflight detail
SHEET 05External door cill and head
SHEET 06Party wall detail

Services

SHEET 07Ventilation 3D
SHEET 08Drainage plan
SHEET 09Electrical schematic
SHEET 10Services plan

Photos

SHEET 11Site survey
SHEET 12Site survey — rear
SHEET 13Site survey — existing conditions
SHEET 14Site survey — rear existing conditions